Skip ads and navigation
Advertising
Our network sites seattlepi.comHelp

Saturday, August 5, 2006

Movement of first section of bridge was a long time coming

THE ASSOCIATED PRESS

TACOMA -- It took about four hours to move one 420-ton piece of steel bridge deck into place below the skeleton of the new Tacoma Narrows Bridge.

But preparation for installing of the bridge deck -- which could begin as early as this weekend -- has taken considerably longer.

It took three weeks for a convoy of cargo ships to transport more than 30 chunks of bridge deck from South Korea to the Puget Sound. Three weeks later, the first of the ships sailed from Commencement Bay to the Tacoma Narrows, a process requiring two attempts when scaffolding on the first vessel was too tall to get under the old bridge. The pieces, averaging 120 feet long by 78 feet wide by 30 feet deep, sat on the boats in the Narrows for another month.

Then it took two attempts for the next step, which was completed this week. On Thursday, crews used powerful cranes and gigantic winches to successfully transfer the bridge's first deck section from a cargo ship anchored in the Narrows to a specially designed barge fighting the current below.

Claudia Cornish, state Transportation Department spokeswoman, said bridge builders were thrilled when a gantry crane lifted the first deck section off the Swan at about 12:30 p.m.

"We've all been working hard for this day," Cornish said. "It's very exciting."

It was only another step in the process, which began in fall 2002.

Over the next few days, crews aboard the barge Marmac will wash off salt that accumulated on the green decking during the 5,200-mile trip from South Korea, where the sections were made. They'll remove braces and supports that held it in place with 15 other deck sections aboard the Swan.

They'll inspect every piece of the more than 400-ton steel structure to make sure it's ready to be hoisted into place.

Then -- maybe this weekend, maybe early next week -- the Marmac will be maneuvered into position so the section can be hoisted and attached to suspender cables at midspan.

It's a two-step process bridge workers will repeat dozens of times over the coming months.

A few of the deck sections will be lifted straight from the Swan into the suspension system, but most will require the ship-to-barge transfer.

"We're talking about the beginning of a six-month process here," Cornish said.

The $849 million project is already three months behind schedule, but Dennis Engel, bridge project engineer for the state, said bridge builder Tacoma Narrows Constructors is still on track to meet the latest completion date of July 2007.

Add P-I Local headlines to
My web site My Yahoo! Google *More options
advertising
INSIDE SEATTLEPI.COM

Day in Pictures

Indonesia's Independence Day and more

Worst spot in your yard

Advice on replacing groundcovers

Rainn Wilson

On Dwight, 'The Rocker' and more
Photo gallery
ADVERTISING
Advertising
OUR AFFILIATES
NWsource KOMO
Pacific Publishing

Seattle Post-Intelligencer
101 Elliott Ave. W.
Seattle, WA 98119
(206) 448-8000

Home Delivery: (206) 464-2121 or (800) 542-0820
seattlepi.com serves about 1.7 million unique visitors
and 30 million page views each month.

Send comments to newmedia@seattlepi.com
Send investigative tips to iteam@seattlepi.com
©1996-2008 Seattle Post-Intelligencer
Terms of Use/Privacy Policy

Hearst Newspapers